Sunday, July 26, 2015

Shed and drainage

Late May to July - the shed, concrete poured for the top of the steps, a place for the bins and the shed slab.  Also build the rest of the steps and did a bit of drainage (70 metres of trenches dug by hand before being filled with agi pipe and 2 metres of 20ml gravel!!!) after the shed was finished.































Flooring

Started the flooring on 6th March 2015 - a 2 day job......finished 2 weeks later on 20th March!!!















Ramp built

We had a bit of a holiday between the 18th December and the end of January.  No electricity in the kitchen because everyone went on holidays, including us - a 3 week trip to Melbourne.

On the 16th February John, Joey and Dave came down and built the ramp on the northern side of the house to give access to the back yard.